I-15 Smart Freeway Pilot Project
Status: Under Construction
Location: Western Riverside County
Type of Project: Highways
Location: Northbound Interstate 15 from the San Diego/Riverside County Line in Temecula to the 15/215 Interchange in Murrieta
Engineering/Environmental Studies: Completed late 2023
Construction: Complete
Investment: $33 million
OVERVIEW
The Riverside County Transportation Commission (RCTC), in partnership with Caltrans, Western Riverside Council of Governments, and the City of Temecula, has implemented innovative technology along the northbound Interstate 15 (I-15) in Temecula and Murrieta that is anticipated to improve traffic operations and enhance travel time reliability for drivers.
Severe congestion occurs along northbound I-15 from the San Diego/Riverside County Line in Temecula to the I-15/I-215 Interchange in Murrieta. This is caused by the high volume of vehicles entering the freeway at the Temecula Parkway, Rancho California Road, and Winchester Road on-ramps, particularly during peak afternoon and evening hours.
The project includes an eight-mile, non-tolled segment equipped with advanced sensors and intelligent transportation system features that continuously monitor real-time traffic conditions. Recently, the project reached a key milestone with the launch of a 90-day baseline data collection period, during which sensors are gathering information on traffic volumes, speeds, and travel times to establish current conditions.
Once the system turns on, adaptive ramp meters will function as a coordinated system, adjusting in real time to allow more or fewer vehicles to enter the freeway. This approach is designed to improve mainline traffic flow, reduce stop-and-go conditions, and enhance travel time reliability. Digital message signs will also display recommended speeds and current conditions along northbound I-15 to help maintain steady traffic flow and improve safety.
While drivers may initially experience short delays at on ramps, the system is expected to result in overall time savings, fewer stops, and smoother travel along the corridor. The system collects traffic flow data only and does not capture photographs, issue tickets, or collect personal information. The pilot project will begin in June and will be evaluated over a two-year period to determine its effectiveness and potential for broader implementation.
The two-year pilot period is expected to begin in late May 2026.
Week of February 27, 2026
Week of December 8, 2025
Week December of 1, 2025
Week of November 6, 2025
Week of October 13, 2025
Digital Sign Testing Alert
Week of September 15, 2025 UPDATED
Week of September 8, 2025
Week of September 2, 2025
Special Construction Update, August 25, 2025
Week of August 25, 2025
Week of August 18, 2025
Week of August 11, 2025
Week of August 4, 2025
Week of July 7, 2025
Week of July 20, 2025
Week of July 13, 2025
Special Construction Update
Week of June 30, 2025
Week of June 16, 2025
Week of June 9, 2025 UPDATE
Week of June 9, 2025
Week of June 2, 2025
Week of May 26, 2025
Week of May 19, 2025
Week of May 11, 2025
Week of May 5, 2025
Week of April 7, 2025
Week of March 24, 2025
Week of January 13, 2025
Week of January 6, 2025
Construction, including installing the ”smart” technology, coordinating the on-ramp signal timing, and placing roadside informational signs, began January 2025 and was completed later that year. In late May 2026, the pilot period will begin for two years.O
During the pilot period, RCTC and Caltrans will evaluate the project to assess its effect on traffic congestion and determine possible expansion of the program statewide. This schedule is subject to change.

- 2019 – RCTC began exploring smart freeway technologies
- March 2022 – RCTC received $5 million of Community Project Funding in the federal Appropriations Omnibus Bill, through the support of Congressman Ken Calvert. The $5 million allocation will complete the $18 million funding package for the I-15 Smart Freeway Pilot Project.
- 2023-2024 – Completion of engineering and environmental studies and final design; release of construction bid
- January 2025 – Construction began on the project.
- May 2026 – Pilot Period Begins
Subscribe for updates on the Interstate 15 Smart Freeway Pilot Project
As part of the I-15 Smart Freeway Pilot Project, crews have installed digital message signs along northbound 15 and at on-ramps.
Join RCTC for an in-person open house meeting for the I-15 Smart Freeway Pilot Project.
In-Person
When: Thursday, March 14, 2024, from 5:30 p.m. – 7:00 p.m.
Location: Temecula City Hall Conference Center
41000 Main Street
Temecula, CA 92590
Virtual
When: Thursday, March 21, 2024, from 6:00 p.m. – 7:00 p.m.
Where: rctc.org/SmartFreewayMeeting

