On mobile devices, swipe left and right to navigate the schedule table.
November 2026
Construction continued this fall on Phase II of the State Route 60/Potrero Boulevard Interchange Project. See the latest improvements taking shape across the project area in September’s Potrero in Progress video below.
Truck Detours
Beginning the week of Monday, November 9, 2026, the westbound SR-60 Western Knolls Avenue on- and off-ramps will be temporarily closed to trucks, freight vehicles, and tractor-trailers as crews work to realign Western Knolls Avenue. The ramps will remain open to passenger vehicles.
During the closure, trucks and freight vehicles will be detoured to Potrero Boulevard and Oak Valley Parkway to access I-10 and reconnect to westbound SR-60. The closure will remain in place 24 hours a day, seven days a week, and is anticipated to continue through spring 2027.
Construction activity will take place on weekdays and include roadway repaving, lane striping, and utility relocation.
We appreciate the community’s patience as we work to deliver this major transportation project. Learn More
Construction activity and schedule are subject to change.

ABOUT THE PROJECT
RCTC and the City of Beaumont, in partnership with Caltrans, is constructing “Phase II” of the SR-60/Potrero Boulevard Interchange Project. This phase includes construction of a six-ramp partial cloverleaf interchange, realignment of Western Knolls Avenue, and widening Potrero Boulevard to six lanes.
Construction began May 2026, and the new interchange is anticipated to open to motorists in 2028. For more information, visit the project webpage.
Email: potrerointerchange@rctc.org
Project Helpline: (951) 200-4158
Text Alerts: Text “Potrero” to (855) 793-2625
Upcoming Work
Construction activity and closures are subject to change due to inclement weather and other factors.
| Date / Time | Activity & Location | Detour |
|---|---|---|
| Tuesday, January 13 – Wednesday, January 14 9 p.m. – 5 a.m. |
Southbound 71 to westbound 91 connector closure | Use eastbound 91 to Serfas Club Dr./Auto Center Dr. off-ramp to westbound 91 |
| Tuesday, January 13 – Wednesday, January 14 10 p.m. – 6 a.m. |
Eastbound 91 Green River Rd. on-ramp | Use Green River Rd. to eastbound Palisades Dr. to northbound Serfas Club Dr./Auto Center Dr. |
Highway Closures
| Date / Time | Activity & Location | Detour |
|---|---|---|
| Monday, August 31 – Wednesday, September 2 Nightly, 10 p.m. – 6 a.m. _________________ Thursday, September 3 – Nightly, 11 p.m. – 6 a.m. |
Single lane closures along eastbound SR-60 from Jack Rabbit Trail to I-10 |
No detour required, since other lanes will remain open |
| Monday, August 31 – Wednesday, September 2 Nightly, 10 p.m. – 6 a.m. _________________ Thursday, September 3 – Nightly, 11 p.m. – 6 a.m. |
Single lane closures along westbound SR-60 from I-10 to Jack Rabbit Trail |
No detour required, since other lanes will remain open |