Week of December 2, 2024
Full Weeknight Closures of Westbound 91 Begin Next Week
The Riverside County Transportation Commission’s 71/91 Interchange Project will require full weeknight (Monday – Wednesday) closures of westbound 91 between the 71 and Green River Rd. in Corona beginning Monday, December 2, 2024. Closures are scheduled through Wednesday, December 18, 2024.
Due to the holidays, no closures will be scheduled from December 20 through January 1, 2025. The full weeknight westbound 91 closures are anticipated to restart on Monday, January 6, 2025. Please be on the lookout for more information.
Sign Up for Project Updates
Highway Lane Closures
Date/Time |
Activity and Location |
Detour |
---|---|---|
Monday, December 2– Wednesday, December 4 Nightly, 10 p.m. – 4 a.m. |
Full closure of westbound 91 from the 91 to Green River Rd. |
Regional Detour |
Monday, December 2 – Wednesday, December 4 Nightly, 8 p.m. – 4 a.m. |
Westbound 91 Express Lanes closed from the I-15 to the County Line |
Regional Detour |
Monday, December 2 – Tuesday, December 5 Nightly, 10 p.m. – 6 a.m. ______________________ Friday, December 6 Midnight – 7 a.m. |
Eastbound 91 alternating lane closures from the County Line to the I-15 |
No detour required, since other lanes will remain open |
Monday, December 2 9 p.m. – 5 a.m. |
Southbound 71 alternating lane closures from Butterfield Ranch Rd. to the 91 |
No detour required, since other lanes will remain open |
Thursday, December 5 8 p.m. – 4 a.m. ____________________ Friday, December 6 10 p.m. – 7 a.m. |
Westbound 91 Express Lanes closures from the I-15 to the County Line |
No detour required, since other lanes will remain open |
Monday, December 2 – Thursday, December 5 Nightly, 10 p.m. – 6 a.m. _____________________ Friday, December 6 11 p.m. – 7 a.m. |
Eastbound 91 Express Lanes closures from the County Line to the I-15 |
No detour required, since other lanes will remain open |
Ramp and Connector Closures
Date/Time |
Activity and Location |
Detour |
---|---|---|
Monday, December 2 – Wednesday, December 4 Nightly, 9 p.m. – 5 a.m. |
Southbound 71 to westbound 91 connector closed |
Use eastbound 91 to Serfas Club Dr./ Auto Center Dr. off-ramp to westbound on-ramp to regional detour |
Monday, December 2 – Thursday, December 5 Nightly, 8 p.m. – 4 a.m. _____________________ Friday, December 6 10 p.m. – 7 a.m. |
Northbound I-15 to westbound 91 Express Lanes connector closed |
No detours required, since other lanes remain open |
Monday, December 2 – Thursday, December 5 Nightly, 8 p.m. – 4 a.m. _____________________ Friday, December 6 10 p.m. – 7 a.m. |
Southbound I-15 to westbound 91 Express Lanes connector closed |
No detours required, since other lanes remain open |
Follow the project:
The Riverside County Transportation Commission, in partnership with Caltrans, is reconstructing the 71/91 Interchange Project in Corona.
The new non-tolled interchange is designed to improve safety, expand access to other modes of travel, reduce greenhouse gas emissions, enhance traffic flow, and support continued movement of native wildlife through the area. Construction will take place from early 2023 to 2025.
To view previous construction updates, please visit the project page.
RIVERSIDE COUNTY TRANSPORTATION COMMISSION
4080 Lemon Street, 3rd Floor
Riverside, CA 92501
Helpline: 800.519.6961
Text 7191INTERCHANGE to 77222
Email: 7191interchange@rctc.org
Project Webpage: rctc.org/71-91interchange
September 2024 Sky Tour Recap
Upcoming Full Westbound 91 Closures
The 71/91 Interchange Project will resume nightly full closures (Monday through Wednesday) of the westbound 91 on Tuesday, January 2 through Wednesday, January 24, 2024.
Due to the holidays, no closures are scheduled through January 1, 2024. Closures will resume on Tuesday, January 2, 2024.
Motorists will need to use the 71, 60, to 57 as alternate routes. For motorists who need to access Green River Road, they may do so by exiting Auto Center Dr./Serfas Club Dr. Fire, police, and emergency responders will have access. We are also informing residents and businesses of detours, traffic expectations, and to allow extra travel time.
Date | Time | Closure Details |
---|---|---|
Monday, February 6 – Friday, February 10 | Nightly, 9 p.m. – 5 a.m. | Southbound 71 alternating lane closures |
Monday, February 6 – Friday, February 10 | Nightly, 9 p.m. – 5 a.m. | Northbound 71 alternating lane closures |
Saturday, February 11 | 12:01 a.m. – 6 a.m. | Southbound 71 alternating lane closures |
Connector and Ramp Closures
Detour routes for all above closures will be maintained at all times. Schedule is subject to change, based on weather and other factors.
Detour Map
Weeknight (Monday - Wednesday) full closures of westbound 91 are scheduled from Monday, December 2 through Wednesday, December 18.
Due to the holidays, no closures will be scheduled from December 20 through January 1, 2025. The westbound 91 full nightly closure are anticipated to restart on Monday, January 6, 2025.
Motorists are highly encouraged to avoid the westbound 91 by using the northbound 71 to westbound 60 to southbound 57 to get around the closure.
For more information, please click here.