PLAN AHEAD FOR EASTBOUND 91 CLOSURESOctober 16, 2023 - November 29, 2023
The Riverside County Transportation Commission’s 71/91 Interchange Project will require nightly full closures (Monday through Wednesday) of the eastbound 91 beginning Monday, October 16, 2023 through Tuesday, November 29, 2023.
These closures will allow crews to safely construct support structures and place beams for the new eastbound 91 to northbound 71 connector. Crews will build a 30 foot tall structure over the 91 and set more than 200 beams over the eastbound and westbound 91 lanes.
Additional nighttime lane reductions, 91 Express Lanes closures in Riverside County, ramp closures, and connector closures will occur Thursday — Sunday nights. Full westbound 91 closures will be scheduled in late 2023 to allow crews to build the structure over westbound 91.
The following closures will be scheduled:
Full Eastbound 91 Closures
Green River Rd. to Serfas Club Dr./Auto Center Dr.
- Nightly, Monday – Wednesday from 11 p.m. to 5 a.m.
Eastbound 91 Express Lanes Closures
From Orange County/Riverside County Line to 15/91 Interchange
- Nightly, Monday – Wednesday from 10 p.m. to 6 a.m.
Eastbound Green River Rd. On-Ramp Closures
Nightly, Monday – Wednesday from 10 p.m. to 6 a.m.
Closure dates are subject to change due to weather, site conditions, construction progress, and other factors.
For the best mobile viewing experience, please rotate your phone.
Date/Time |
Activity and Location |
Detour |
---|---|---|
Friday, June 9 9 p.m. – 7 a.m. ________________________ Saturday, June 10 9 p.m. – 7 a.m. ________________________ Sunday, June 11 9 p.m. – 7 a.m. |
Eastbound 91 Green River Rd. on-ramp closed | Use Green River Rd. to eastbound Palisades Dr. to northbound Serfas Club Dr./Auto Center Dr. to eastbound 91
See detour map below |
Friday, June 9 at 9 p.m. – Monday, June 11 at 5 a.m. | Full closures of eastbound and westbound 91 Express Lanes in Riverside County | No detour required, since other lanes will remain open. Expect heavy traffic |
Saturday, June 10 1 a.m. – 7 a.m. ________________________ Sunday, June 11 1 a.m. – 7 a.m. ________________________ Monday, June 12 1 a.m. – 5 a.m. |
⚠️FULL CLOSURE: All eastbound 91 lanes from Green River Rd. to Serfas Club Dr. | See detour map below |
FULL CLOSURES
Eastbound 91, Green River Rd. to Serfas Club Dr./Auto Center Dr.
- Saturday, June 10 from 1 a.m. – 7 a.m.
- Sunday, June 11 from 1 a.m. – 7 a.m.
- Monday, June 12 from 1 a.m. – 7 a.m.
WEEKEND FULL CLOSURES
Eastbound and Westbound 91 Express Lanes, Riverside County
- Friday, June 9 at 9 p.m. to Monday, June 12 to 5 a.m.
NIGHTTIME FULL CLOSURES
Eastbound 91 Green River Rd. On-Ramp
- Friday, June 9 at 9 p.m. to Saturday, June 10 at 7 a.m.
- Saturday, June 10 at 9 p.m. to Sunday, June 11 at 7 a.m.
- Sunday, June 11 at 9 p.m. to Monday, June 12 at 5 a.m.
Eastbound Alternate Routes
Eastbound travelers should use northbound 57 to eastbound 60 to southbound 71 to eastbound 91 to reach eastbound destinations. Motorists may also use the eastbound 91 at Green River Rd. to Palisades Dr. to Serfas Club Dr. to reenter the eastbound 91. Expect heavy traffic delays.
Regional Detour
Local Detour
Residents should expect traffic congestion on streets near the 91 and 71 and should plan for extra time to reach local destinations. Fire, police, and ambulance services will have access to emergency response. During these closures, heavy traffic delays are expected for motorists traveling on the 91 and 71 through Corona.
Follow the project:
The Riverside County Transportation Commission, in partnership with Caltrans, is reconstructing the 71/91 Interchange Project in Corona.
The new non-tolled interchange is designed to improve safety, expand access to other modes of travel, reduce greenhouse gas emissions, enhance traffic flow, and support continued movement of native wildlife through the area. Construction will take place from early 2023 to 2025.
RIVERSIDE COUNTY TRANSPORTATION COMMISSION
4080 Lemon Street, 3rd Floor
Riverside, CA 92501
Helpline: 800.519.6961
Text 7191INTERCHANGE to 77222
Email: 7191interchange@rctc.org
Project Webpage: rctc.org/71-91interchange
Date | Time | Closure Details |
---|---|---|
Monday, February 6 – Friday, February 10 | Nightly, 9 p.m. – 5 a.m. | Southbound 71 alternating lane closures |
Monday, February 6 – Friday, February 10 | Nightly, 9 p.m. – 5 a.m. | Northbound 71 alternating lane closures |
Saturday, February 11 | 12:01 a.m. – 6 a.m. | Southbound 71 alternating lane closures |