Current Projects:
60/215 East Junction Interchange Project
- Build two direct connectors closing the gap between the SR-60 westbound HOV lane in Moreno Valley and the 60/215 eastbound HOV lane
- Modify and realign north 215/Box Springs exit ramp
- Realign and widen Box Springs Road to four lanes
Construction Start Date: Summer 2011
Construction End Date:Summer 2014
Estimated Cost: $43 million
Current Status: Under Construction


SR-60
- Add truck climbing lane, Badlands area, east of Moreno Valley
Completed Projects:
60/215 Additional Lanes
- EB Truck Lane Connecting to 1-215 Southbound
- EB Truck Lane from University Avenue to Day Street
- University Avenue to 60/215 Interchange
SR-60 Additional Lanes
- 60/215 Interchange to Redlands Boulevard
- 1-15 to Valley Way